AB “ORLEN Lietuva”

PROJECT NAME: LCN AND HCN DIRECTION TO GASOLINE BLENDING SEPARATELY

  • Installation of pipelines of LCN from PRIME G+ viawater coolervia LPG storing tanks to blending station;
  • Scope ofstage: Installation of ~ 5.5 new km. pipelines, installation of three new pumps, implementation of  cold tie-ins. This piping system allows to make separate blending of LCN throughout all the year (including warm season) . All works done in 3 month.